The Ontario Energy Board granted Hydro One conditional leave to build a roughly 205-kilometre, 500-kilovolt line from Hanmer transformer station in Greater Sudbury to Mississagi station near Wharncliffe, generally following an existing corridor.
In its November 19, 2026 decision, EB-2026-0154, the board said Ontario’s priority designation required it to accept the need for the line. It separately assessed prices, reliability and Ontario’s economic growth policies and found the project in the public interest.
The board accepted the capital estimate plus $2 million in removal costs, citing competitive procurement. It said Hydro One had not fully explained the rise from a preliminary $650-million estimate. The projected 79-cent monthly increase for a typical household was not an approved rate; spending may face later review.
The board approved the forms of land agreements, not individual land rights. Hydro One still needs required permits and rights and must meet system and customer impact requirements. Unless the board orders otherwise, the authorization lapses if construction does not start within 12 months.