The Nova Scotia Energy Board approved the Independent Energy System Operator’s $14.85 million expenditure and revenue requirement for 2026–27, including $1.77 million in transition costs.
In its November 2, 2026 decision, 2026 NSEB 25, the board considered the spending reasonable for a new operator taking on functions from Nova Scotia Power. It nevertheless required better-supported forecasts, clearer cost categories and stronger procurement oversight.
The operator argued that section 29(4) of the More Access to Energy Act allowed only approval as filed or referral back. The board concluded that it could also reduce or amend proposed amounts, avoiding delays and protecting ratepayers before costs were incurred. It did not cut the request here.
The board approved a permanent mechanism for tracking differences between actual and approved amounts, but required safeguards before recovery. It retained quarterly reporting and left the broader fee recovery mechanism to a separate proceeding. The formal order sets July 2, 2027 as the deadline for procurement policies and cost-allocation guidelines.
In a separate 2027–28 proceeding, M13173, the board’s notice sets November 23, 2026 for formal intervention requests. Written comments and requests to speak are due February 8, 2027; the hearing starts February 22.