The Canada Energy Regulator has approved Trans Mountain’s negotiated toll settlement, allowing long-term firm contracts to cover up to 90 per cent of the pipeline system’s nominal capacity from January 1, 2027 and ending the outstanding interim-tolls hearing.
In its September 28, 2026 letter decision, File 7067319, the Commission found the settlement produced just and reasonable tolls without unjust discrimination. It approved the package and associated contracting process through Order TO-005-2026, despite Tsleil-Waututh Nation’s request for further scrutiny of the agreement’s financial and safety implications.
The decision increased the permitted share of firm contracting from 80 to 90 per cent. The Commission accepted that meaningful access would remain for shippers without long-term contracts, while acknowledging that the capacity available to them could be constrained in individual months.
A settlement replaces the contested toll hearing
The approximately 1,180-kilometre pipeline system runs from Edmonton to Burnaby and transports crude oil and refined petroleum products to British Columbia destinations, including the Westridge Marine Terminal. Its expansion raised nominal capacity from about 300,000 to 890,000 barrels a day.
Trans Mountain applied for interim commencement tolls in June 2023. Those tolls took effect when the expanded system began operating in May 2024, while a regulatory proceeding continued to examine outstanding issues. The Commission paused that proceeding in October 2025 to allow commercial negotiations.
Seven of the eight original firm-service shippers signed the settlement filed in July 2026. The package establishes a new tolling framework and amended transportation agreements from January 1, 2027, finalizes interim tolls for the preceding period, terminates facility-support agreements and provides for the release of certain claims. Approval also cancelled proceeding RH-002-2023.
Trans Mountain’s related open season offered 93,500 barrels a day of firm capacity. That consisted of 10 per cent of the system’s nominal capacity plus 4,500 barrels a day that had not previously been contracted. Ten bids resulted in allocations to three bids under the advertised procedures.
Commercial support did not eliminate the public-interest test
Under the Commission’s settlement guidelines, the negotiation process must be open to and understood by interested parties, must not restrict the regulator’s consideration of the broader public interest, and must leave enough information on the public record to evaluate the result.
No party with a commercial interest opposed the settlement. The Commission accepted the staged negotiations, which began with a smaller group of firm shippers before expanding to the remaining shippers and other interested parties. It found no need for a further public hearing.
Tsleil-Waututh Nation opposed expedited approval. It argued that lower tolls and inadequate returns could undermine Trans Mountain’s ability to pay for maintenance, safety and spill response, affecting its territory and rights. It also challenged the allocation of expansion costs and the company’s commercial discipline. The group PIPEUP took no position on approval but sought assurance that environmental and incident-response resources would remain adequate.
The Commission considered those submissions but found neither group had demonstrated an interest affected by the settlement or compelling public-interest grounds for further process. It said the settlement authorized no new physical changes, and the Nation had not identified specific effects on Aboriginal title or other rights arising from this toll decision.
The Commission also rejected the asserted connection between the settlement and inadequate safety funding. It emphasized that pipeline safety, financial-resources and abandonment-funding obligations continued regardless of the toll methodology. The reasons identify a $1.1-billion financial-resources requirement for releases from the expanded system. This was the Commission’s answer to the funding concern, not a finding that pipeline operations pose no risk.
Access for shippers without firm contracts
The Commission separately examined Trans Mountain’s common-carrier obligation. Its framework requires fair and equal access to firm service and sufficient remaining capacity for uncommitted shipments, including the needs of smaller and future shippers.
It found the open season appropriate because the terms were communicated transparently, potential bidders had equal access and Trans Mountain responded to feedback. It also accepted evidence that the system could be expanded and that uncommitted capacity was expected to average approximately 10 per cent of nominal capacity over a year.
That was not a guarantee of 10 per cent availability every month. The Commission acknowledged that available capacity could fall to or below 90 per cent of nominal capacity in some months, affecting uncommitted access. Its conclusion relied partly on operating evidence showing average available capacity slightly above nominal capacity following expansion start-up.
The existing allocation procedures remained in place, and the Commission found sufficient uncommitted capacity would remain at Westridge to support marine deliveries. A separate application concerning additional contracting tied to the drag-reducing-agent expansion was not decided in this proceeding.
Future tariff filings remain open to challenge
Trans Mountain did not need advance permission to file the fixed component of uncommitted tolls and adjustments under paragraph 229(1)(a) of the Canadian Energy Regulator Act. That provision permits charging a toll specified in a filed tariff that is in effect.
However, the Commission said this filing route was for routine, non-controversial matters. Shippers and other interested parties retained the right to dispute a filing, and the Commission could consider those concerns and establish further proceedings. The approval therefore did not remove regulatory oversight of future tariff changes.