The Mackenzie Valley Environmental Impact Review Board confirmed on November 13, 2026, that the statutory clock on Imperial Oil’s Norman Wells closure and reclamation assessment was paused. In EA2526-01, the board said it could not define the scope of the assessment without a sufficiently developed draft final closure plan. The board ordered the assessment in April 2025 but did not yet have enough information to set its scope.
The board applied subsection 128(2.4) of the Mackenzie Valley Resource Management Act, which excludes time the proponent takes to supply required information. The board will decide when the plan gives it enough detail to scope the review and will notify parties when the clock resumes. Preparations, including engagement with Indigenous governments and communities, can continue.
This is separate from two assessments the board cancelled in March after Imperial withdrew applications to replace a flowline and extend operations. The November determination neither approved the closure plan nor ended its assessment.