The Canada Energy Regulator has approved a lower operating-pressure ceiling for Trans-Northern Pipelines Inc.’s Ottawa Lateral and removed the line from a safety order, finding that changed operating requirements and demonstrated compliance resolved the concerns behind its inclusion.
The Commission’s June 1, 2026 decision and Order AO-016-SO-T217-03-2010, File 4668651 set a maximum of 4,619 kilopascals for all five sections of the nominal 12-inch pipeline. The ruling did not authorize a return to the higher pressures in its original approvals.
A lower limit instead of restored pressure
Trans-Northern applied on August 7, 2025 to vary five operating-pressure orders and remove the Ottawa Lateral from Schedule C of the broader safety order.
The original approvals allowed different pressures for different sections: 8,274 kilopascals for two sections, and 8,095, 8,955 and 10,170 kilopascals for the others. The pipeline had been subject to a safety-related pressure restriction since September 2016. At the time of the application, the maximum under that restriction was 8,274 kilopascals.
Rather than ask to restore the original higher approvals, the company sought a single lower ceiling reflecting changed throughput requirements. That distinction mattered: the decision combined relief from a particular safety order with a reduction in approved pressure, not an increase.
Changed circumstances and engineering evidence
Under section 69 of the Canadian Energy Regulator Act, the Commission may review, change or rescind its orders. Its reasons describe a cautious two-stage approach. An applicant must first raise doubt about the correctness of the existing decision, including through changed circumstances or new facts. An application must also explain the prejudice or damage caused, or expected to be caused, by the order. The Commission then decides whether to leave it in place or change it.
The change in throughput requirements met the first stage for the pressure approvals. The Commission was also satisfied that Trans-Northern had shown the pipeline could operate safely at 4,619 kilopascals.
The supporting material included an annual engineering assessment submitted in December 2024, an engineering assessment and standards-compliance report accompanying the application, and responses to the regulator’s further information requests.
For removal from the safety order, the Commission relied on two developments together: the new lower pressure ceiling and Trans-Northern’s demonstration that it had met conditions 4.a through 4.e, which applied across its pipeline system. It concluded that the safety concerns responsible for including this line in the order had been resolved.
Six orders, with limits on the relief
The Commission issued five amending orders to put the new pressure ceiling into the section-specific approvals. A sixth order removed the Ottawa Lateral from Schedule C. Because it was the schedule’s last remaining pipeline, Schedule C was deleted entirely.
The decision also warned Trans-Northern about the quality of future applications. It said deficiencies had to be corrected before relief could be granted and referred the company to concerns raised in an earlier decision about demonstrating current fitness for service.
The result concerns the Ottawa Lateral and the specified approvals. It does not cancel the wider safety order for the rest of Trans-Northern’s system or establish that every pipeline operated by the company is free of safety concerns.